We are extremely excited to share details of our Capital Works Project to aid the transition of year 7 students into secondary school in 2022.
The school has been assigned $13.8m for the construction of a new building as well as the refurbishment of some older spaces to support contemporary learning.
- Completed Works
- School Refurbishment
- New Building
- Impact on Site Access
- Contact Us
- Photo Library
We are extremely excited to share details of our Capital Works Project to aid the transition of year 7 students into secondary school in 2022.
The school has been assigned $13.8m for the construction of a new building as well as the refurbishment of some older spaces to support contemporary learning.
COMPLETED WORKS
At the start of Term 4, 2020, Brighton Secondary School took handover of Stage 1 of the Capital Works Project. The oval realignment and construction of our new volleyball courts has been completed and students have already commenced using this newly finished resource. |
|
SCHOOL REFURBISHMENT
Refurbishments will be taking place on the upper floor of the Spence wing of the school, which is the oldest building on the site. The refurbishment works will take place from Monday 2 November 2020 until the start of Term 1 2021. Once complete, the refurbishment will provide:
From Monday 16 November, the lower level of the building will reopen for students to be able to use their lockers again, however, students upstairs will need to carry their bags for the remainder of the year. We have a limited number of spare lockers across the rest of the site, which students can request access to via Student Reception during this period if they require a locker for this period.
Refurbishments will be taking place on the upper floor of the Spence wing of the school, which is the oldest building on the site. The refurbishment works will take place from Monday 2 November 2020 until the start of Term 1 2021. Once complete, the refurbishment will provide:
- 6 general learning spaces updated for contemporary learning.
- A learning common for classroom breakout.
- A fresh staff preparation space designed to bring teams together.
From Monday 16 November, the lower level of the building will reopen for students to be able to use their lockers again, however, students upstairs will need to carry their bags for the remainder of the year. We have a limited number of spare lockers across the rest of the site, which students can request access to via Student Reception during this period if they require a locker for this period.
NEW BUILDING
Our new building is expected to be completed mid 2021 and has been specifically designed for use by our Middle School students. It will be located along the north perimeter of the school between the Volleyball Stadium and Performing Arts Centre.
Our new building is expected to be completed mid 2021 and has been specifically designed for use by our Middle School students. It will be located along the north perimeter of the school between the Volleyball Stadium and Performing Arts Centre.
|
Across 2 levels the contemporary learning building will contain:
This portion of the project is progressing well and we are excited to see the building starting to take shape. |
IMPACT ON SITE ACCESS
Construction Zone
Construction Zone
The main construction compound will remain for the length of the project (minimum 12 months). All buildings will be accessible however, some access routes may change.
Timelines and Dates
Both the Concert Hall and Theatre will remain in operation and both venues will remain accessible, however, there will be some narrowed walkways to the front of the venues, due to the close proximity to the construction site. Loading dock and rear access to the venues is unavailable for the duration of the project.
Parking and Traffic
Traffic conditions in surrounding streets and within carparks may be altered. Please comply with all signed conditions and drive safely.
For the safety of all people during the project, student:
For after hours, please consider the altered access and allow additional time to park.
Timelines and Dates
- HASS and Languages refurbishment – Monday 2 November 2020 until beginning of Term 1 2021
Both the Concert Hall and Theatre will remain in operation and both venues will remain accessible, however, there will be some narrowed walkways to the front of the venues, due to the close proximity to the construction site. Loading dock and rear access to the venues is unavailable for the duration of the project.
Parking and Traffic
Traffic conditions in surrounding streets and within carparks may be altered. Please comply with all signed conditions and drive safely.
For the safety of all people during the project, student:
- Drop off
- Pick up
- Parking
For after hours, please consider the altered access and allow additional time to park.
CONTACT USShould you have any questions or concerns regarding these works, please contact us on 08 8375 8200 or email facilities@brighton.sa.edu.au
Information from the Department for Education is available at: https://www.education.sa.gov.au/sites-and-facilities/upgrades-and-new-schools/major-school-upgrades/brighton-secondary-school
Information from the Department for Education is available at: https://www.education.sa.gov.au/sites-and-facilities/upgrades-and-new-schools/major-school-upgrades/brighton-secondary-school